When a major social media company prevented blasting from occurring during an expansion of the server buildings, the contractor and blasting company reached out to Deep Earth Logic to partner in meeting with the owner to explain the blasting process and how the vibrations could be controlled to prevent any harm from occurring at the existing servers and electrical infrastructure. Over forty (40) blasts later, with a major portion of the blasts occurring within 100 feet), the rock was safely excavated with zero impact on the operating servers. Deep Earth Logic’s scientific approach to the project eliminated any doubt about the control and safety of the daily blasting and resulting vibration as quantified by Peak Particle Velocity, frequency, and acceleration.